PMO Operations Intelligence
Three AI agents review the portfolio and raise findings. They never change project data.
Agents
Budget overruns, clusters of red-health projects and other portfolio control exceptions.
Executive brief content, management decision context and leadership agenda priorities.
Weekly executive brief
Week of 19 October 2026. Prepared by the Chief-of-Staff agent from portfolio data. No project data was changed.
Portfolio headline
The portfolio needs attention. Seven of ten projects are on or near plan, but the two largest programmes carry the delay and the cost pressure.
Decisions needed
- Approve a recovery plan for the ATC Systems Upgrade, 13 points behind plan.
- Decide on extended support for the legacy ATC systems before the equipment order date.
- Resume or cancel the Remote Tower Feasibility Study.
Financial position
Total budget AED 357.0M, actual cost AED 224.5M (63%). One project is over budget: Accident Investigation Case System, by AED 0.4M.
Top risks
- Equipment delivery slips past the 9-month lead time (score 20).
- Cutover disrupts live control service (score 15).
- Operators do not register in time on the Drone Registration Platform (score 12).
Outlook
If the ATC recovery plan is agreed this week, the portfolio SPI is expected to return above 0.95 within two months.
Open findings
CriticalDelivery Assurance
ATC Systems Upgrade is 13 points behind plan
Progress is 66% against 79% planned (SPI 0.84). Late equipment delivery and late vendor design documents are the main causes.
Recommended: Agree a dated recovery plan with the vendor and review the schedule at the next steering committee.
HighPortfolio Control
Accident Investigation Case System has spent more than its budget
Actual cost is AED 9.9M against a budget of AED 9.5M (CPI 0.86), with 10% of the work left.
Recommended: Request a budget variance note and decide whether to approve a change request.
HighDelivery Assurance
Aeronautical Information Management System has SPI 0.88 and CPI 0.87
Both indexes are below 0.90 while the project is still in planning.
Recommended: Re-baseline the plan before the project moves to execution.
MediumDelivery Assurance
17 tasks are overdue, 9 of them in the ATC Systems Upgrade
Overdue tasks cluster around vendor deliveries and training bookings.
Recommended: Ask project managers to confirm owners and new dates.
MediumPortfolio Control
Remote Tower Feasibility Study is on hold at 15% against 30% planned
AED 0.9M is spent and the project has had no update for 6 weeks.
Recommended: Confirm whether to resume or cancel, and release any committed budget.
InfoChief-of-Staff
Decision needed: extended support on the legacy ATC systems
Option A in the ATC business case must be decided before the equipment order date.
Recommended: Add the decision to the next leadership agenda.
No open findings.
Recent runs
- Daily review
6 findings - Data-change check
1 finding - Weekly brief
Brief sent to the PMO Manager - Manual portfolio review
5 findings
People stay responsible for every decision and action. Visible to Admin and PMO Manager users.